If 12 persons working 12 hours a day dig 12 meters of a tunnel in 12 days, how many men are required to dig additional 04 meters of the tunnel(of the same dimension) given that they work 04 hours a day for 04 days ?

[A] 27
[B] 4
[C] 12
[D] 36
Loading...
Next Question

Overall Stats

Attempted 66
Correct 13
Incorrect 15
Viewed 38

Answers

Guest
Guest
Vijaykant Dubey
Vijaykant Dubey - 5 months ago

Vijaykant Dubey is saying 4 is correct answer

V.M.Singh
V.M.Singh - 1 year ago

V.M.Singh from Ludhiana, India is saying 4 is correct answer

Amit Kumar Singh
Amit Kumar Singh - 2 years ago

Amit Kumar Singh from India is saying 36 is correct answer

Nazia Sayed
Nazia Sayed - 2 years ago

Nazia Sayed from Mumbai, India is saying 36 is correct answer

ashi yadav
ashi yadav - 3 years ago

ashi yadav from Auraiya, India is saying 36 is correct answer

Related Questions

Dr B R Ambedkar clashed with Mahatma Gandhi at the 2nd Round Table Conference demanding ?

  • [A] Reservation for Dalits in Government jobs
  • [B] Reservation for Dalits in Ministries
  • [C] Separate citizen status for Dalits
  • [D] Separate Electorate for Dalits

In a triangle ABC, one of the angles is average of the remaining two angles. Which of the following is always true about the triangle ABC ?

  • [A] Isosceles triangle
  • [B] Equilateral triangle
  • [C] One of its angles measures 60 degree.
  • [D] Right angles triangle