A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

[A] 5
[B] 5 <sup>1</sup>/<sub>2</sub>
[C] 6
[D] 8
[E] None of these