2 years ago in Time and Work

A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?

[A] 11:30 A.M.
[B] 12 noon
[C] 12:30 P.M.
[D] 1:00 P.M.
Loading...
Next Question

Overall Stats

Attempted 1
Correct 0
Incorrect 1
Viewed 0

Answers

Guest
Guest
Amit Garg
Amit Garg - 1 year ago

Amit Garg is saying 12 noon is correct answer

Related Questions