If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

[A] 4 days
[B] 5 days
[C] 6 days
[D] 7 days