A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

[A] Rs. 375
[B] Rs. 400
[C] Rs. 600
[D] Rs. 800