Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take 8/3 more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs, 450, then in how many days did A, B and C together complete the whole work?

[A] 2
[B] 4
[C] 6
[D] 8
[E] 10