2 years ago in Time and Work

A, B and C completed a work costing Rs. 1800. A work for 6 days, B for 4 days and c for 9 days. If their daily wages are in the ratio of 5:6:4, how much amount will be received by A?

[A] Rs. 800
[B] Rs. 600
[C] Rs. 900
[D] Rs. 750