Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in:

[A] 3 days
[B] 4 days
[C] 4.5 days
[D] 5.4 days