2 years ago in Table Chart

Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. the number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)

[A] 150%
[B] 225%
[C] 270%
[D] 240%
Loading...

Directions (16-20): Tech Vinayak software company before selling a package to its clients, follows the given schedule.


Next Question

Overall Stats

Attempted 2
Correct 0
Incorrect 0
Viewed 2

Answers

Guest
Guest

Related Questions